This tutorial contains a video and a written guide how to make and use a top plot from multiple datas. This tutorial operates with pre-made profiles, surfaces, XYZ points and layers.
Requirements
1. Right clik profile in “Object manager” → “Show Profile Window”.
2. Rightclick the terrain in Object Manager → Object Properties → profile click “Show In Top Plot” correct “Top Plot Axis: right” → OK (refresh the profile).
3. To edit the top plot axe in “Profile2” go to Object Manager and right click “Profile2” → Oobject Properties → General → in the Top Plot menu. Here the right axe is set from 30 to 120.
1. Repeat step 2.2. just rightclick the XYZ points in Object Manager and check if the point values are listed on the left side axis.
2. Rightclick XYZ points in Object Manager → Object Properties → Data → Edit… → Configure Dataset… → Preview Data….
3. Repeat step 2.3. just for the left side axis and check if the axis values need to be corrected according to the values of the XYZ data points.